New Elementary School (Battin Replacement) |
|
The new grade Pre-K to 8 school will be built on the District-owned Joseph Battin School site. The school will be designed to educate a maximum of approximately 1,000 students in a 146,000 square-foot facility. The project scope includes demolition of the existing Battin School in advance of construction of the new facility. |
CURRENT STATUS - As of February 1, 2026: The design-build design phase is ongoing. The contractor has mobilized to the site and construction activities are expected to commence within the next month.
|
PROJECT INFORMATION
|
Key Parties:
|
Bridging Design Consultant |
STV, Inc. |
|
Early Site Preparation Contractor |
USA Environmental Management, Inc. |
|
Design-Build Contractor |
Terminal Construction Corp. |
|
Design-Build Architect |
DMR Architects, Inc. |
|
Construction Manager |
Accenture Infrastructure and Capital Projects, LLC |
Schedule*:
|
Design |
Design NTP September 2025 |
|
Start of Building Construction |
TBD |
|
Anticipated School Opening |
September 2028 |
Costs:
|
Total Estimated Project Costs |
$101.2 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|