|
|
New Elementary School (Battin Replacement) |
|
The new grade Pre-K to 8 school will be built on the District-owned Joseph Battin School site. The school will be designed to educate a maximum of approximately 1,000 students in a 142,000 square-foot facility. The project scope includes demolition of the existing Battin School in advance of construction of the new facility. |
CURRENT STATUS - As of August 1, 2025: The early site preparation activities are complete. A design-build award to Terminal Construction was approved by the Board of Directors in July 2025. A construction management procurement was advertised on June 30, 2025.
|
PROJECT INFORMATION
|
Key Parties:
|
Bridging Design Consultant |
STV, Inc. |
|
Early Site Preparation Contractor |
USA Environmental Management, Inc. |
|
Design-Build Contractor |
Terminal Construction Corp. |
|
Design-Build Architect |
DMR Architects, Inc. |
|
Construction Manager |
TBD |
Schedule*:
|
Design |
Design NTP TBD |
|
Start of Building Construction |
TBD |
|
Anticipated School Opening |
TBD |
Costs:
|
Total Estimated Project Costs |
$96.2 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|