New Elementary School (Battin Replacement) |
The new grade Pre-K to 8 school will be built on the District-owned Joseph Battin School site. The school will be designed to educate a maximum of approximately 1,000 students in a 142,000 square-foot facility. The project scope includes demolition of the existing Battin School in advance of construction of the new facility. |
CURRENT STATUS - As of March 15, 2025: Early site work and demolition activities of the existing school are nearing completion. A design-build contract advertisement was issued on March 4, 2025.
|
PROJECT INFORMATION
|
Key Parties:
Early Site Preparation Contractor |
USA Environmental Management, Inc. |
Design-Build Contractor |
TBD |
Design-Build Architect |
TBD |
Construction Manager |
TBD |
Schedule*:
Design |
Design NTP TBD |
Start of Building Construction |
TBD |
Anticipated School Opening |
TBD |
Costs:
Total Estimated Project Costs |
$96.2 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|