New ES at Halloran PS 22 Site |
The new 140,000 square-foot, four story school was designed to educate approximately 890 students in grades two through eight. The school includes 34 general use classrooms, three self-contained special education classrooms, six science demonstration rooms and labs, a gymnasium, a cafeteria, a multi-purpose room with stage, a media center and administrative offices. The new school was built using a design-build approach.
|
CURRENT STATUS - The project is substantially complete and the school is occupied. |
PROJECT INFORMATION
|
Key Parties:
Design-Build Contractor |
Torcon |
Design-Build Architect |
USA Architects |
Construction Manager |
EPIC Management, Inc. |
Schedule*:
Design |
NTP issued December 16, 2014 |
Start of Building Construction |
NTP issued November 5, 2015 |
School Opening |
September 2017 |
Costs:
Total Project Costs |
$55.3 Million |
Total Construction Costs |
$40.6 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|