New Perth Amboy High School |
The New Perth Amboy High School will be designed to educate a maximum of approximately 3,300 students in 9th to 12th grade. The project scope calls for construction of a new, three-story, approximately 576,000 square foot facility. |
CURRENT STATUS - As of March 1, 2024: The project is in the final stages of construction. Installation of furniture and technology throughout the building is ongoing. Final building inspections are ongoing. The school is on track for an early delivery in Spring 2024.
|
PROJECT INFORMATION
|
Key Parties:
Design-Build Contractor |
Terminal Construction Corp. |
Design-Build Architect |
RSC Architects |
Construction Manager |
Cambridge Construction Management, Inc. |
Schedule*:
Design |
Design NTP 1/15/20 |
Start of Building Construction |
TBD |
Anticipated School Opening |
September 2024 |
Costs:
Total Estimated Project Costs |
$283.8 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|