New Middle School |
|
The new school will be designed to be an approximately 162,000 square-foot facility to educate a maximum of 876 students in grades 6 to 8. |
CURRENT STATUS - As of March 2, 2026: The design-build design phase is ongoing. An award for construction management services was approved at the February 4 Board of Directors Meeting.
|
PROJECT INFORMATION
|
Key Parties:
|
Bridging Design Consultant |
SSP Architectural Group, Inc. |
|
Design-Build Contractor |
Terminal Construction Corporation |
|
Design-Build Architect |
DMR Architects |
|
Construction Manager |
EPIC Management |
|
Early Site Preparation Contractor |
APS Contracting, Inc. |
Schedule*:
|
Design |
Design NTP 11/25/25 |
|
Start of Building Construction |
TBD |
|
Anticipated School Opening |
September 2028 |
Costs:
|
Total Estimated Project Costs |
$121.8 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|