New Middle School |
The new school will be designed to be an approximately 147,000 square-foot facility to educate approximately 788 students in grades 6 to 8. |
CURRENT STATUS - As of June 1, 2025: The preliminary project charter was approved by the SDA Board of Directors at the March 2024 meeting. An early site preparation contract was awarded to APS Contracting, Inc. on May 16, 2025. A design-build procurement is anticipated for Q2/Q3 2025.
|
PROJECT INFORMATION
|
Key Parties:
Design-Build Contractor |
TBD |
Design-Build Architect |
TBD |
Construction Manager |
TBD |
Early Site Preparation Contractor |
TBD |
Schedule*:
Design |
Design NTP TBD |
Start of Building Construction |
TBD |
Anticipated School Opening |
TBD |
Costs:
Total Estimated Project Costs |
$110.1 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|