|
|
New Middle School |
|
The new school will be designed to be an approximately 162,000 square-foot facility to educate a maximum of 876 students in grades 6 to 8. |
CURRENT STATUS - As of October 1, 2025: Early site preparation activities are ongoing to ready the site for future construction of a new school. A design-build contract award was approved by the Board of Directors at the October 1 Board Meeting. A construction management procurement is anticipated for Q4 2025/Q1 2026.
|
PROJECT INFORMATION
|
Key Parties:
|
Design-Build Contractor |
TBD |
|
Design-Build Architect |
TBD |
|
Construction Manager |
TBD |
|
Early Site Preparation Contractor |
APS Contracting, Inc. |
Schedule*:
|
Design |
Design NTP TBD |
|
Start of Building Construction |
TBD |
|
Anticipated School Opening |
September 2028 |
Costs:
|
Total Estimated Project Costs |
$121.8 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|