Cleveland Street Elementary School |
The project included the construction of an approximately 11,500 square-foot addition and renovations to the existing Cleveland Street Elementary School.
|
CURRENT STATUS - The project is substantially complete and occupied.
|
PROJECT INFORMATION
|
Key Parties:
Site Preparation/Demolition Construction Contractor |
Two Brothers Construction |
General Contractor |
Terminal Construction |
Architect |
Kliment Halsband Architects |
Construction Manager |
EPIC Management. |
Schedule*:
Site Preparation Construction Activities |
Completed May 2019 |
Design |
Design NTP 12/3/2017 |
Start of Building Construction |
October 2019 |
School Opening |
September 2024 |
Costs:
Total Estimated Project Costs |
$51.7 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|