Orange
Cleveland Street E.S.

335 CLEVELAND ST

ORANGE, NJ 07050-1916

(973)677-4100



Cleveland Street Elementary School
The project will include the construction of an approximately 11,500 square-foot addition and renovations to the existing Cleveland Street Elementary School to accomodate a Pre-Kindergarten to 8th grade program.

CURRENT STATUS - As of March 1, 2024: The project is in construction. Site work, masonry detailing, carpentry, and window installation are ongoing. Installation of finishes such as epoxy flooring, paint, ceramic tile, flooring and gym equipment are also ongoing.

PROJECT INFORMATION

Key Parties:
Site Preparation/Demolition Construction Contractor Two Brothers Construction
General Contractor Terminal Construction
Architect Kliment Halsband Architects
Construction Manager EPIC Management.

Schedule*:
Site Preparation Construction Activities Completed May 2019
Design Design NTP 12/3/2017
Start of Building Construction October 2019
Anticipated School Opening September 2024

Costs:
Total Estimated Project Costs $51.7 Million






*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.