Cleveland Street Elementary School |
The project will include the construction of an approximately 11,500 square-foot addition and renovations to the existing Cleveland Street Elementary School to accomodate a Pre-Kindergarten to 8th grade program.
|
CURRENT STATUS - As of February 1, 2023: A procurement for general construction services was advertised on January 30, 2023. Bid are due April 5, 2023.
|
PROJECT INFORMATION
|
Key Parties:
Site Preparation/Demolition Construction Contractor |
Two Brothers Construction |
General Contractor |
Brockwell & Carrington Contractors |
Architect |
Kliment Halsband Architects |
Construction Manager |
EPIC Management. |
Schedule*:
Site Preparation Construction Activities |
Completed May 2019 |
Design |
Design NTP 12/3/2017 |
Start of Building Construction |
October 2019 |
Costs:
Total Estimated Project Costs |
$33.2 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|