Cleveland Street Elementary School |
The project will include the construction of an approximately 11,500 square-foot addition and renovations to the existing Cleveland Street Elementary School to accomodate a Pre-Kindergarten to 8th grade program.
|
CURRENT STATUS - As of March 1, 2024: The project is in construction. Site work, masonry detailing, carpentry, and window installation are ongoing. Installation of finishes such as epoxy flooring, paint, ceramic tile, flooring and gym equipment are also ongoing.
|
PROJECT INFORMATION
|
Key Parties:
Site Preparation/Demolition Construction Contractor |
Two Brothers Construction |
General Contractor |
Terminal Construction |
Architect |
Kliment Halsband Architects |
Construction Manager |
EPIC Management. |
Schedule*:
Site Preparation Construction Activities |
Completed May 2019 |
Design |
Design NTP 12/3/2017 |
Start of Building Construction |
October 2019 |
Anticipated School Opening |
September 2024 |
Costs:
Total Estimated Project Costs |
$51.7 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|