Millville Senior High School |
The project includes the construction of a 228,544 square-foot addition and 54,950 square feet of renovations/alterations. The additions/renovations will increase student capacity to accommodate a maximum of approximately 2,380 students in 9th to 12th grade. |
CURRENT STATUS - As of February 1, 2023: Interior finishes on the Phase IV addition of the auditorium are ongoing. All Phase III and Phase IV interior renovations are complete and occupied. The Phase II addition opened to students in September 2020. The Phase III North addition opened to students in September 2021.
|
PROJECT INFORMATION
|
Key Parties:
Design-Build Contractor |
Hall Construction |
Design-Build Architect |
PS&S |
Construction Manager |
Greyhawk North America, LLC |
Schedule*:
Design |
Design NTP 2/11/2016 |
Start of Building Construction |
5/24/2017 |
Anticipated School Opening |
Phased |
Costs:
Total Estimated Project Costs |
$137.5 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|