New Elementary School (School #5 Replacement) |
The new grade K to 5 school will be built on the District-owned Woodrow Wilson School #5 site. The school will be designed to educate a maximum of approximately 850 students in a 132,000 square-foot facility. The project scope included demolition of the existing Woodrow Wilson School No. 5 in advance of construction of the new facility. |
CURRENT STATUS - As of September 1, 2025: The project is in construction. A groundbreaking ceremony was held on August 26, 2025.
|
PROJECT INFORMATION
|
Key Parties:
Early Site Preparation Contractor |
APS Contracting, Inc. |
Design-Build Contractor |
Dobco, Inc. |
Design-Build Architect |
NK Architects |
Construction Manager |
Accenture, part of Anser Advisory Management LLC |
Schedule*:
Design |
Design NTP January 24, 2025 |
Start of Building Construction |
June 25, 2025 |
School Opening |
September 2027 |
Costs:
Total Estimated Project Costs |
$87.6 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|