Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
---|---|---|---|---|
EL-0044-N01 | Elizabeth | New Pre-K - 8 School | 09/29/2023 | 12/12/2023 |
Firm | Final Project Limit |
---|---|
APS Contracting, Inc. | $21,339,919.00 |
Caravella Demolition, Inc. | $1,983,508.00 |
Gramercy Group, Inc. | $29,902,625.00 |
Intercontinental Construction Contracting Inc. | $18,296,957.00 |
JPC Group, Inc. | $105,175,870.00 |
Richard E Pierson Construction Co., Inc. | $3,343,402.00 |
USA Environmental Management, Inc. | $13,828,295.00 |
Vollers Excavating & Construction, Inc. | $18,706,563.00 |
Winzinger, Inc. | $3,456,172.00 |