| Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
|---|---|---|---|---|
| ST-0021-C01 | Bridgeton | Bridgeton HS - Media Center and Elevator Addition | 11/25/2003 | 07/21/2004 |
| Firm | Final Project Limit |
|---|---|
| Altchem Environmental Services, Inc. | $4,000,000.00 |
| Arthur J. Ogren, Inc. | $18,216,000.00 |
| Coastal Land Contractors, Inc. | $915,000.00 |
| Dolan Mechanical Inc. | $2,332,000.00 |
| Fanelli Construction, Inc. | $2,863,500.00 |
| Fletcher-Harlee Corp | $10,650,000.00 |
| H&S Construction & Mech., Inc. | $7,200,000.00 |
| Horizon Group Of N.E. Inc | $6,307,876.50 |
| John D. Lawrence, Inc. | $6,375,000.00 |
| Martell Construction Co Inc | $5,680,950.00 |
| Orba Construction Corp. | $6,012,319.50 |
| Stanker & Galetto, Inc. | $16,719,000.00 |
| Wu & Associates, Inc. | $6,391,128.80 |