| Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
|---|---|---|---|---|
| ST-0007-C01 | Millville | Lakeside M.S. Fine & Performing Arts Center & Gymnasium Addition | 08/14/2003 | 11/05/2003 |
| Firm | Final Project Limit |
|---|---|
| Arthur J. Ogren, Inc. | $18,216,000.00 |
| Daniel J. Keating Constr.Co. t/a Keating Bldg | $117,000,000.00 |
| Ernest Bock & Sons, Inc. | $77,760,000.00 |
| Fred M. Schiavone Construction, Inc. | $9,246,000.00 |
| Imperial Construction Group, Inc. | $16,200,000.00 |
| Lighton Electric, Inc. | $14,878,122.60 |
| Sambe Construction Co., Inc. | $16,065,000.00 |
| Stanker & Galetto, Inc. | $16,719,000.00 |
| Turner Construction Company | $126,000,000.00 |