| Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
|---|---|---|---|---|
| ET-0013-C01 | Neptune Township | New Midtown Community Center | 08/21/2003 | 11/13/2003 |
| Firm | Final Project Limit |
|---|---|
| Bovis Lend Lease, Inc. | $600,000,000.00 |
| Daniel J. Keating Constr.Co. t/a Keating Bldg | $117,000,000.00 |
| Ernest Bock & Sons, Inc. | $77,760,000.00 |
| Hunt Construction Group, Inc. | $556,250,000.00 |
| Petracca & Sons, Inc. | $67,230,660.00 |
| Prismatic Development Corp. | $124,500,000.00 |
| Railroad Construction Co Inc | $146,458,350.55 |
| Seacoast Builders Corp. | $26,250,000.00 |
| Skanska USA Building, Inc. | $438,000,000.00 |
| Terminal Construction Corp. | $106,560,000.00 |
| Torcon, Inc. | $261,900,000.00 |
| Tri-Con Constr Co. of N. Jersey | $16,649,100.00 |
| Turner Construction Company | $126,000,000.00 |