| Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
|---|---|---|---|---|
| EP-0113-C01 | Paterson | PS #5 - Roof Replacement, Masonry & Window Repairs | 02/12/2021 | 04/21/2021 |
| Firm | Final Project Limit |
|---|---|
| APS Contracting, Inc. | $15,000,000.00 |
| Brockwell & Carrington Contractors, Inc. | $23,061,457.00 |
| D.A. Nolt, Inc. | $21,743,988.00 |
| DMD Contracting, LLC | $34,674,648.00 |
| Duall Building Restoration, Inc. | $21,779,823.00 |
| Ernest Bock & Sons, Inc. | $160,454,097.00 |
| GL Group, Inc. | $13,704,480.00 |
| Grove Contracting LLC | $3,861,572.00 |
| Hall Building Corporation | $37,332,790.00 |
| Hall Construction Co., Inc. | $141,684,711.00 |
| Lighton Electric, Inc. | $11,912,369.00 |
| Mak Group, LLC | $4,072,858.00 |
| Masonry Preservation Group, Inc. | $21,779,823.00 |
| Morganti Group Inc. (The) | $133,668,815.00 |
| Paul Otto Building Co., Inc. | $15,252,411.00 |
| Pravco, Inc. | $4,181,183.00 |
| Rising Sun Construction, LLC | $24,056,289.00 |