Contract No. | Contract Name & Location | School District |
---|---|---|
WT-0022-N01 | Trenton Central High School | Trenton |
Firm | Final Project Limit |
---|---|
AP Construction, Inc. | $54,120,000.00 |
D&K Construction Co., Inc. | $42,239,685.18 |
Dobco, Inc. | $100,860,000.00 |
Dobtol Construction, LLC | $9,187,500.00 |
Hall Building Corporation | $47,384,387.54 |
Hall Construction Co., Inc. | $127,929,280.00 |
Luzon, Inc. | $10,533,168.00 |
Meco Constructors, Inc. | $12,520,750.00 |
Neuber Environmental Services, Inc. | $14,000,000.00 |
Paul Otto Building Co., Inc. | $32,235,449.40 |
Tricon Enterprises, Inc. | $3,900,988.00 |
Two Brothers Contracting, Inc. | $4,721,663.00 |
USA Environmental Management, Inc. | $10,553,168.00 |
Yannuzzi Group, Inc. | $14,175,233.80 |
NJSDA Price and Other Factors
Bid Opening Worksheet
Contract Name: Trenton Central High School
Contract Number: WT-0022-N01
School District:Trenton
Firm | Sub Consultants | Bid Amount | Price Points |
Price Rank |
Non Price Points |
Non Price Rank |
Weighted Price Points |
Weighted Non- Price Points |
Total Points | Final Rank |
---|---|---|---|---|---|---|---|---|---|---|
Luzon, Inc. | View | $8,496,870.00 | 100.000 | 1 | 74.250 | 1 | 80.000 | 14.850 | 94.850 | 1 |
USA Environmental Management, Inc. | View | $8,496,870.00 | 100.000 | 1 | 74.250 | 1 | 80.000 | 14.850 | 94.850 | 1 |
Meco Constructors, Inc. | View | $9,654,710.38 | 86.373 | 2 | 66.250 | 3 | 69.099 | 13.250 | 82.349 | 2 |
Neuber Environmental Services, Inc. | View | $9,691,823.31 | 85.937 | 3 | 67.813 | 2 | 68.749 | 13.563 | 82.312 | 3 |
Paul Otto Building Co., Inc. | View | $12,174,123.00 | 56.722 | 4 | 41.500 | 4 | 45.378 | 8.300 | 53.678 | 4 |
Notes: