Contract No. | Contract Name & Location | School District |
---|---|---|
NT-0014-N02 | James Madison E.S. #10 | Garfield |
Firm | Final Project Limit |
---|---|
Bismark Construction Corp. | $8,147,250.00 |
GL Group, Inc. | $1,737,500.00 |
K M Construction Corp | $2,556,000.00 |
Kario Construction Corp. | $9,695,367.00 |
Montana Construction Corp. Inc. | $18,169,923.00 |
Neelam Construction Corp | $17,491,350.00 |
Silverlands Services, Inc. | $2,126,250.00 |
SMAC Corp | $3,284,400.00 |
Tricon Enterprises, Inc. | $1,950,494.00 |
Two Brothers Contracting, Inc. | $4,551,000.00 |
USA Environmental Management, Inc. | $7,278,672.00 |
Yannuzzi Group, Inc. | $13,254,764.00 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
Tricon Enterprises, Inc. | $1,057,000.00 | View |
Two Brothers Contracting, Inc. | $1,218,319.00 | View |
USA Environmental Management, Inc. | $1,342,732.00 | View |
Neelam Construction Corp | $1,353,073.10 | View |
SMAC Corp | $1,376,100.00 | View |
Bismark Construction Corp. | $1,484,578.00 | View |
Silverlands Services, Inc. | $1,574,444.00 | View |
Gramercy Group, Inc. | $1,645,256.46 | View |
GL Group, Inc. | $1,700,572.40 | View |
Yannuzzi Group, Inc. | $1,995,000.00 | View |