Contract No. | Contract Name & Location | School District |
---|---|---|
NE-0015-C01 | McKinley ES | Newark |
Firm | Final Project Limit |
---|---|
Bennett Company, Inc. (The) | $10,871,537.00 |
Bergen Engineering Co. | $37,815,360.00 |
Cobra Construction Co., Inc. | $27,930,000.00 |
D&K Construction Co., Inc. | $33,300,000.00 |
Komi Construction Inc. | $24,173,558.00 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
Cobra Construction Co., Inc. | $10,550,000.00 | View |
Bennett Company, Inc. (The) | $10,771,800.00 | View |
D&K Construction Co., Inc. | $10,848,000.00 | View |
Bergen Engineering Co. | $10,860,718.00 | View |
Komi Construction Inc. | $12,888,000.00 | View |