Contract No. | Contract Name & Location | School District |
---|---|---|
NE-0009-P01 | Speedway PK 8 Elementary | Newark |
Firm | Final Project Limit |
---|---|
All Pro Contracting, LLC | $1,710,241.00 |
B&N&K Restoration Co., Inc. | $5,291,000.00 |
D&K Construction Co., Inc. | $33,300,000.00 |
PSP Construction, Inc. | $1,547,500.00 |
Slavco Construction, Inc. | $4,727,323.00 |
Tricon Enterprises, Inc. | $2,000,000.00 |
Two Brothers Contracting, Inc. | $1,877,750.00 |
V. Ottilio & Sons, Inc. | $1,312,000.00 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
Tricon Enterprises, Inc. | $437,000.00 | View |
Slavco Construction, Inc. | $569,000.00 | View |
V. Ottilio & Sons, Inc. | $569,287.00 | View |
D&K Construction Co., Inc. | $644,644.00 | View |
All Pro Contracting, LLC | $777,795.00 | View |
Two Brothers Contracting, Inc. | $848,100.00 | View |
PSP Construction, Inc. | $951,000.00 | View |