Contract No. | Contract Name & Location | School District |
---|---|---|
JE-0001-C02 | New Heights Middle School | Jersey City |
Firm | Final Project Limit |
---|---|
APS Contractors, Inc. | $7,288,380.00 |
B&N&K Restoration Co., Inc. | $4,810,000.00 |
Brockwell & Carrington | $6,328,000.00 |
Cobra Construction Co., Inc. | $23,534,853.00 |
Conti Enterprises Inc | $57,900,000.00 |
Horizon Group Of N.E. Inc | $6,307,876.50 |
Mazzocchi Wrecking, Inc. | $25,974,580.50 |
Niram Inc. | $7,100,000.00 |
Orba Construction Corp. | $6,012,319.50 |
Yannuzzi Group, Inc. | $46,134,000.00 |
Firm | Sub Contractors |
---|---|
Conti Enterprises Inc | View |
Niram Inc. | View |
Yannuzzi Group, Inc. | View |
Firm | Bid Amount | Sub Contractors |
---|---|---|
Yannuzzi Group, Inc. | $2,146,900.00 | View |
Conti Enterprises Inc | $2,377,732.00 | View |
Mazzocchi Wrecking, Inc. | $2,691,000.00 | View |
Niram Inc. | $2,930,000.00 | View |