Contract No. | Contract Name & Location | School District |
---|---|---|
HU-0004-P01 | New Schlemm ECC | Union City |
Firm | Final Project Limit |
---|---|
B&N&K Restoration Co., Inc. | $5,328,000.00 |
Cobra Construction Co., Inc. | $13,697,397.00 |
Delric Construction Co., Inc. | $4,020,000.00 |
R&J Construction, Inc. | $1,968,509.85 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
B&N&K Restoration Co., Inc. | $864,000.00 | View |
Cobra Construction Co., Inc. | $870,000.00 | View |
Delric Construction Co., Inc. | $950,000.00 | View |
R&J Construction, Inc. | $1,198,000.00 | View |