Contract No. | Contract Name & Location | School District |
---|---|---|
EL-0044-N01 | New Pre-K - 8 School | Elizabeth |
Firm | Final Project Limit |
---|---|
APS Contracting, Inc. | $21,339,919.00 |
Caravella Demolition, Inc. | $1,983,508.00 |
Gramercy Group, Inc. | $29,902,625.00 |
Intercontinental Construction Contracting Inc. | $18,296,957.00 |
JPC Group, Inc. | $105,175,870.00 |
Richard E Pierson Construction Co., Inc. | $3,343,402.00 |
USA Environmental Management, Inc. | $13,828,295.00 |
Vollers Excavating & Construction, Inc. | $18,706,563.00 |
Winzinger, Inc. | $3,456,172.00 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
USA Environmental Management, Inc. | $5,855,000.00 | View |
APS Contracting, Inc. | $6,819,000.00 | View |
Gramercy Group, Inc. | $9,783,000.00 | View |
JPC Group, Inc. | $11,100,000.00 | View |