| Contract No. | Contract Name & Location | School District |
|---|---|---|
| WT-0011-C03 | New MLK/Jefferson ES | Trenton |
| Firm | Final Project Limit |
|---|---|
| Cobra Construction Co., Inc. | $30,240,000.00 |
| Ernest Bock & Sons, Inc. | $70,200,000.00 |
| Hall Construction Co., Inc. | $57,504,960.00 |
| Hunter Roberts Construction Group, LLC | $92,933,379.00 |
| Tamburro Bros. Const. Co., Inc | $17,165,759.00 |
| Terminal Construction Corp. | $172,550,000.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Hall Construction Co., Inc. | $35,477,000.00 | View |
| Terminal Construction Corp. | $36,885,000.00 | View |
| Ernest Bock & Sons, Inc. | $37,467,000.00 | View |