| Contract No. | Contract Name & Location | School District |
|---|---|---|
| ST-0009-C01 | New Pre-K to 8 | Fairfield |
| Firm | Final Project Limit |
|---|---|
| Arthur J. Ogren, Inc. | $18,216,000.00 |
| Ernest Bock & Sons, Inc. | $77,220,000.00 |
| Fred M. Schiavone Construction, Inc. | $9,100,000.00 |
| Horizon Group Of N.E. Inc | $13,914,000.00 |
| Imperial Construction Group, Inc. | $16,200,000.00 |
| Lighton Electric, Inc. | $14,427,270.40 |
| Martell Construction Co Inc | $5,491,585.00 |
| Stanker & Galetto, Inc. | $16,719,000.00 |
| Tamburro Bros. Const. Co., Inc | $14,640,000.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Imperial Construction Group, Inc. | $13,136,000.00 | View |
| Stanker & Galetto, Inc. | $13,188,000.00 | View |
| Ernest Bock & Sons, Inc. | $13,447,000.00 | View |
| Arthur J. Ogren, Inc. | $13,469,000.00 | View |