| Contract No. | Contract Name & Location | School District |
|---|---|---|
| NT-0032-C02 | Clark Schools (4) rehab | Clark |
| Firm | Final Project Limit |
|---|---|
| Barrett Roofs, Inc. | $1,465,033.65 |
| D.A. Nolt, Inc. | $2,568,333.00 |
| E.R. Barrett, Inc. | $1,903,169.84 |
| G&M Eastern Contracting Inc | $4,542,781.50 |
| Horizon Group Of N.E. Inc | $6,307,876.50 |
| Safeway Contracting, Inc. | $1,708,000.00 |
| Winchester Roofing Corp | $2,178,000.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Safeway Contracting, Inc. | $1,138,900.00 | View |
| G&M Eastern Contracting Inc | $1,327,000.00 | View |
| Horizon Group Of N.E. Inc | $1,492,000.00 | View |
| Winchester Roofing Corp | $1,925,000.00 | View |
| D.A. Nolt, Inc. | $1,947,673.00 | View |