| Contract No. | Contract Name & Location | School District |
|---|---|---|
| NE-0008-P01 | West Side HS Site Improvements - SBE Set-Aside | Newark |
| Firm | Final Project Limit |
|---|---|
| APS Contractors, Inc. | $6,036,840.00 |
| B&N&K Restoration Co., Inc. | $5,032,000.00 |
| Cobra Construction Co., Inc. | $13,697,397.00 |
| Horizon Group Of N.E. Inc | $6,307,877.00 |
| Occidental Construction Co., Inc. | $5,330,000.00 |
| Site Contractors Inc. | $3,796,000.00 |
| Slavco Construction, Inc. | $2,069,401.00 |
| Tec-Con Contractors Inc. | $3,351,130.00 |
| Tri-Con Constr Co. of N. Jersey | $19,465,280.00 |
| Tricon Enterprises, Inc. | $2,000,000.00 |
| V. Ottilio & Sons, Inc. | $1,045,250.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Occidental Construction Co., Inc. | $2,087,087.00 | View |
| Tec-Con Contractors Inc. | $2,279,000.00 | View |
| APS Contractors, Inc. | $2,790,000.00 | View |