| Contract No. | Contract Name & Location | School District |
|---|---|---|
| HU-0015-C01 | PS #2 ES | West New York |
| Firm | Final Project Limit |
|---|---|
| Bergen Engineering Co. | $40,343,380.00 |
| Brockwell & Carrington Contractors, Inc. | $13,005,000.00 |
| Chanree Construction Co Inc | $15,087,794.00 |
| Cobra Construction Co., Inc. | $30,240,000.00 |
| D&K Construction Co., Inc. | $50,650,600.00 |
| Delric Construction Co., Inc. | $40,134,216.00 |
| Hall Construction Co., Inc. | $57,504,960.00 |
| Paul Otto Building Co., Inc. | $24,137,574.00 |
| Prismatic Development Corp. | $117,030,000.00 |
| Vanas Construction Co., Inc. | $40,674,819.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| D&K Construction Co., Inc. | $20,387,387.00 | View |
| Delric Construction Co., Inc. | $21,310,000.00 | View |
| Paul Otto Building Co., Inc. | $21,670,000.00 | View |
| Vanas Construction Co., Inc. | $23,400,000.00 | View |
| Cobra Construction Co., Inc. | $23,420,000.00 | View |