| Contract No. | Contract Name & Location | School District |
|---|---|---|
| HU-0008-P01 | New Magnet K-8 | Union City |
| Firm | Final Project Limit |
|---|---|
| All Pro Contracting, LLC | $1,710,241.00 |
| Altchem Environmental Services, Inc. | $1,477,583.00 |
| Niram Inc. | $4,666,389.00 |
| Occidental Construction Co., Inc. | $6,384,067.00 |
| Site Contractors Inc. | $4,719,197.00 |
| Slavco Construction, Inc. | $4,861,431.00 |
| Two Brothers Contracting, Inc. | $1,920,000.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| All Pro Contracting, LLC | $1,400,000.00 | View |
| Site Contractors Inc. | $1,501,697.00 | View |
| Slavco Construction, Inc. | $1,525,126.75 | View |
| Niram Inc. | $1,835,984.64 | View |
| Occidental Construction Co., Inc. | $1,943,999.00 | View |