| Contract No. | Contract Name & Location | School District |
|---|---|---|
| HU-0007-C01 | Replacement PS 4 | West New York |
| Firm | Final Project Limit |
|---|---|
| AMCC Corporation | $55,968,000.00 |
| Eastern Contractors Inc. dba Motwane Construction | $48,032,577.00 |
| Joseph A. Natoli Construction Corp. | $45,820,032.39 |
| Petracca & Sons, Inc. | $91,140,000.00 |
| Pike Construction Co | $92,230,573.50 |
| Prismatic Development Corp. | $124,500,000.00 |
| Terminal Construction Corp. | $123,033,500.00 |
| Torcon, Inc. | $261,900,000.00 |
| VRH Construction Corp. | $207,000,000.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Prismatic Development Corp. | $25,300,000.00 | View |
| Pike Construction Co | $26,312,888.00 | View |
| VRH Construction Corp. | $26,595,000.00 | View |
| Torcon, Inc. | $26,997,000.00 | View |
| AMCC Corporation | $27,789,000.00 | View |