| Contract No. | Contract Name & Location | School District |
|---|---|---|
| HU-0001-C03 | Harrison High School Expanded Site Work | Harrison |
| Firm | Final Project Limit |
|---|---|
| Amba Construction Corp. | $1,350,000.00 |
| Horizon Group Of N.E. Inc | $6,307,876.50 |
| NCC, Inc. | $2,040,000.00 |
| PSP Construction, Inc. | $1,547,500.00 |
| Tec-Con Contractors Inc. | $3,373,620.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Tec-Con Contractors Inc. | $526,000.00 | View |
| PSP Construction, Inc. | $818,000.00 | View |