Contract No. | Contract Name & Location | School District |
---|---|---|
ET-0100-N01 | New Plainfield Elementary School | Plainfield |
Firm | Final Project Limit |
---|---|
Caravella Demolition, Inc. | $916,349.00 |
Niram Inc. | $26,935,281.00 |
Santorini Construction Inc. | $10,250,700.00 |
Tricon Enterprises, Inc. | $10,175,150.00 |
Two Brothers Contracting, Inc. | $4,721,663.00 |
USA Environmental Management, Inc. | $15,000,000.00 |
Yannuzzi Group, Inc. | $14,430,470.00 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
Two Brothers Contracting, Inc. | $1,644,444.00 | View |
Tricon Enterprises, Inc. | $1,670,000.00 | View |
Niram Inc. | $2,085,000.00 | View |
Yannuzzi Group, Inc. | $2,265,483.00 | View |
Santorini Construction Inc. | $2,475,000.00 | View |
USA Environmental Management, Inc. | $2,975,000.00 | View |