| Contract No. | Contract Name & Location | School District |
|---|---|---|
| ET-0002-C02 | Barnegat High School | Barnegat Township |
| Firm | Final Project Limit |
|---|---|
| Ernest Bock & Sons, Inc. | $72,360,000.00 |
| Hall Building Corporation | $36,153,275.00 |
| Lighton Electric, Inc. | $19,152,694.00 |
| Ray Angelini Inc | $12,439,224.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Hall Building Corporation | $11,345,000.00 | View |
| Ernest Bock & Sons, Inc. | $11,567,000.00 | View |
| Ray Angelini Inc | $11,585,000.00 | View |
| Lighton Electric, Inc. | $11,795,000.00 | View |