| Contract No. | Contract Name & Location | School District |
|---|---|---|
| ES-0043-C02 | Cleveland Street E.S. | Orange |
| Firm | Final Project Limit |
|---|---|
| Benard Associates Inc. | $49,128,000.00 |
| Bennett Company, Inc. (The) | $56,227,893.00 |
| Delric Construction Co., Inc. | $121,211,709.00 |
| Dobco, Inc. | $144,500,000.00 |
| Ernest Bock & Sons, Inc. | $143,439,924.00 |
| Hall Building Corporation | $55,814,369.00 |
| Hall Construction Co., Inc. | $138,875,267.00 |
| Joseph A. Natoli Construction Corp. | $71,660,082.00 |
| Morganti Group Inc. (The) | $106,148,765.00 |
| Niram Inc. | $49,811,821.00 |
| SMBA Construction, LLC | $7,104,000.00 |
| Terminal Construction Corp. | $239,967,924.00 |
| Worth Construction Co., Inc. | $41,000,000.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Terminal Construction Corp. | $19,434,958.00 | View |
| Ernest Bock & Sons, Inc. | $23,245,000.00 | View |
| Niram Inc. | $23,987,000.00 | View |
| Worth Construction Co., Inc. | $24,170,565.00 | View |
| Morganti Group Inc. (The) | $26,133,398.00 | View |