| Contract No. | Contract Name & Location | School District |
|---|---|---|
| ES-0008-C02 | Lincoln ES | Orange |
| Firm | Final Project Limit |
|---|---|
| B&N&K Restoration Co., Inc. | $5,217,000.00 |
| Circle-A Construction Company, Inc. | $8,253,537.00 |
| D&K Construction Co., Inc. | $50,650,600.00 |
| Hilt Construction Inc | $1,960,971.00 |
| Salazar & Associates, Inc. | $1,194,177.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Hilt Construction Inc | $1,639,891.00 | View |
| Circle-A Construction Company, Inc. | $1,655,000.00 | View |
| D&K Construction Co., Inc. | $1,698,698.00 | View |
| B&N&K Restoration Co., Inc. | $1,890,000.00 | View |