| Contract No. | Contract Name & Location | School District |
|---|---|---|
| ES-0008-C01 | Lincoln ES | Orange |
| Firm | Final Project Limit |
|---|---|
| Bergen Engineering Co. | $40,343,380.00 |
| Chanree Construction Co Inc | $13,374,488.00 |
| Cobra Construction Co., Inc. | $30,240,000.00 |
| D&K Construction Co., Inc. | $50,650,600.00 |
| Delric Construction Co., Inc. | $40,134,216.00 |
| Hall Building Corporation | $39,768,602.00 |
| Hall Construction Co., Inc. | $57,504,960.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Hall Building Corporation | $28,965,000.00 | View |
| Hall Construction Co., Inc. | $28,965,000.00 | View |
| Cobra Construction Co., Inc. | $30,148,000.00 | View |
| Delric Construction Co., Inc. | $31,962,000.00 | View |
| D&K Construction Co., Inc. | $32,497,497.00 | View |