| Contract No. | Contract Name & Location | School District |
|---|---|---|
| EP-0020-C01 | Sharp ES - Emergent Work - Roof Replacement | Camden |
| Firm | Final Project Limit |
|---|---|
| Alper Enterprises, Inc. | $5,085,550.00 |
| Arch-Concept Construction, Inc. | $2,400,000.00 |
| Belcher Roofing Corporation | $3,607,740.00 |
| D.A. Nolt, Inc. | $3,209,038.00 |
| EDA Contractors, Inc. | $4,758,285.00 |
| G&M Eastern Contracting Inc | $3,371,383.00 |
| Integrity Roofing, Inc. | $2,620,000.00 |
| Jottan, Inc. | $8,064,000.00 |
| Laurant Construction Co., Inc. | $1,322,400.00 |
| Robert Ganter Contractors, Inc. | $1,586,000.00 |
| United States Roofing Corporation | $7,212,833.00 |
| Winchester Roofing Corp | $3,685,040.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Winchester Roofing Corp | $178,000.00 | View |
| D.A. Nolt, Inc. | $196,146.00 | View |
| United States Roofing Corporation | $196,700.00 | View |
| Integrity Roofing, Inc. | $198,000.00 | View |
| G&M Eastern Contracting Inc | $202,000.00 | View |
| Robert Ganter Contractors, Inc. | $207,755.00 | View |
| Alper Enterprises, Inc. | $225,000.00 | View |
| Jottan, Inc. | $229,887.00 | View |
| Belcher Roofing Corporation | $237,390.00 | View |