| Contract No. | Contract Name & Location | School District |
|---|---|---|
| EL-0007-P01 | New PreK-8 School #31 | Elizabeth |
| Firm | Final Project Limit |
|---|---|
| Cobra Construction Co., Inc. | $14,689,962.00 |
| Damon G. Douglas Company | $26,250,000.00 |
| Horizon Group Of N.E. Inc | $6,307,876.50 |
| Orba Construction Corp. | $6,012,319.20 |
| Ray Angelini Inc | $12,439,223.94 |
| Tri-Con Constr Co. of N. Jersey | $16,649,100.00 |
| Firm | Sub Contractors |
|---|---|
| Orba Construction Corp. | View |
| Tri-Con Constr Co. of N. Jersey | View |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Cobra Construction Co., Inc. | $4,136,000.00 | View |
| Horizon Group Of N.E. Inc | $4,462,000.00 | View |
| Ray Angelini Inc | $4,486,000.00 | View |
| Tri-Con Constr Co. of N. Jersey | $4,782,000.00 | View |