| Contract No. | Contract Name & Location | School District |
|---|---|---|
| CA-0005-C01 | Dudley ES - New Construction | Camden |
| Firm | Final Project Limit |
|---|---|
| AP Construction, Inc. | $46,368,000.00 |
| Cobra Construction Co., Inc. | $30,240,000.00 |
| D&K Construction Co., Inc. | $50,650,600.00 |
| Hall Building Corporation | $39,768,602.00 |
| Hall Construction Co., Inc. | $57,504,960.00 |
| Hunter Roberts Construction Group, LLC | $92,933,379.00 |
| Paul Otto Building Co., Inc. | $24,137,574.00 |
| Tamburro Bros. Const. Co., Inc | $17,165,759.00 |
| Terminal Construction Corp. | $172,550,000.00 |
| Firm | Bid Amount | Sub Contractors |
|---|---|---|
| Cobra Construction Co., Inc. | $21,430,000.00 | View |
| Paul Otto Building Co., Inc. | $21,467,000.00 | View |
| Hall Building Corporation | $22,225,000.00 | View |
| Hunter Roberts Construction Group, LLC | $22,630,000.00 | View |
| D&K Construction Co., Inc. | $22,987,000.00 | View |
| AP Construction, Inc. | $26,849,000.00 | View |