Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
---|---|---|---|---|
NT-0014-C03 | Garfield | James Madison E.S. #10 | 06/30/2015 | 09/24/2015 |
Firm | Final Project Limit |
---|---|
Brockwell & Carrington Contractors, Inc. | $43,695,683.00 |
D&K Construction Co., Inc. | $42,239,685.00 |
Delric Construction Co., Inc. | $127,315,895.00 |
Dobco, Inc. | $100,860,000.00 |
Ernest Bock & Sons, Inc. | $130,481,150.00 |
Hall Building Corporation | $50,721,316.00 |
Integrated Construction Enterprises, Inc. | $15,168,116.00 |
M&M Construction Company, Inc. | $19,557,000.00 |
Michael Riesz & Co. | $22,988,220.00 |
Niram Inc. | $50,025,000.00 |
Paul Otto Building Co., Inc. | $32,695,956.00 |
Prismatic Development Corp. | $241,792,500.00 |
Terminal Construction Corp. | $212,681,000.00 |
Vanas Construction Co., Inc. | $63,118,805.00 |