Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
---|---|---|---|---|
NT-0001-C01 | Garfield | Garfield Middle School | 04/13/2004 | 07/13/2004 |
Firm | Final Project Limit |
---|---|
AMCC Corporation | $60,452,000.00 |
Chanree Construction Co Inc | $11,305,887.30 |
Eastern Contractors Inc. dba Motwane Construction | $73,093,052.20 |
Ernest Bock & Sons, Inc. | $77,760,000.00 |
HRH Construction Company | $152,440,000.00 |
Leon D. DeMatteis Construction Corp. | $296,876,400.00 |
Petracca & Sons, Inc. | $67,229,637.09 |
Prismatic Development Corp. | $124,500,000.00 |
Railroad Construction Co Inc | $151,508,638.50 |
Terminal Construction Corp. | $132,589,500.00 |
Torcon, Inc. | $261,900,000.00 |
Turner Construction Company | $126,000,000.00 |
VRH Construction Corp. | $207,000,000.00 |