Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
---|---|---|---|---|
EP-0061-C01 | Orange | Orange M.S. - Emergent Work - Roof and Masonry | 03/20/2014 | 04/23/2014 |
Firm | Final Project Limit |
---|---|
Askari Construction, Inc. | $1,545,629.00 |
B&N&K Restoration Co., Inc. | $5,860,317.00 |
D.A. Nolt, Inc. | $8,337,441.00 |
ML, Inc. | $1,118,400.00 |
MTB, LLC | $3,853,051.00 |
Pravco, Inc. | $13,453,506.00 |
Rici Corporation | $2,723,000.00 |
SMAC Corp | $3,284,400.00 |
USA General Contractors Corp | $4,161,780.00 |