Contract No. | School District | General Description | Advertisement Date |
Proposal Due Date |
---|---|---|---|---|
EL-0006-N01 | Elizabeth | New Academic High School | 12/05/2011 | 01/18/2012 |
Firm | Final Project Limit |
---|---|
Aurora Environmental, Inc. | $1,890,000.00 |
Brockwell & Carrington | $29,508,772.80 |
D&K Construction Co., Inc. | $50,965,200.00 |
Luzon, Inc. | $3,933,000.00 |
Site Contractors Inc. | $1,504,000.00 |
Slavco Construction, Inc. | $10,000,000.00 |
SMAC Corp | $2,310,666.84 |
Tomco Construction, Inc. | $15,000,000.00 |
Tricon Enterprises, Inc. | $2,085,945.40 |
Underground Utilities Corporation | $5,317,792.28 |
USA Environmental Management, Inc. | $6,985,572.69 |