Contract No. | Contract Name & Location | School District |
---|---|---|
ST-0046-B01 | Millville Senior High School | Millville |
Firm | Final Project Limit |
---|---|
Daniel J. Keating Company | $108,000,000.00 |
Dobco, Inc. | $144,019,723.00 |
Epic Management, Inc. | $245,490,000.00 |
Ernest Bock & Sons, Inc. | $169,622,902.00 |
Hall Construction Co., Inc. | $153,723,281.00 |
T.N. Ward Company | $656,100,000.00 |
Terminal Construction Corp. | $199,471,000.00 |
Tutor Perini Building Corp. | $785,533,309.00 |
Firm | Sub Consultants | Bid Amount | Price Points |
Price Rank |
Non Price Points |
Non Price Rank |
Weighted Price Points |
Weighted Non- Price Points |
Total Points | Final Rank |
---|---|---|---|---|---|---|---|---|---|---|
Hall Construction Co., Inc. | View | $114,453,000.00 | 99.105 | 2 | 70.625 | 2 | 59.463 | 28.250 | 87.713 | 1 |
Epic Management, Inc. | View | $113,437,217.00 | 100.000 | 1 | 66.208 | 4 | 60.000 | 26.483 | 86.483 | 2 |
Ernest Bock & Sons, Inc. | View | $121,463,000.00 | 92.925 | 4 | 74.917 | 1 | 55.755 | 29.967 | 85.722 | 3 |
Terminal Construction Corp. | View | $130,000,000.00 | 85.399 | 5 | 66.750 | 3 | 51.239 | 26.700 | 77.939 | 4 |
Dobco, Inc. | View | $118,500,000.00 | 95.537 | 3 | 50.667 | 5 | 57.322 | 20.267 | 77.589 | 5 |
Notes: