Contract No. | Contract Name & Location | School District |
---|---|---|
ET-0099-B01 | Perth Amboy High School | Perth Amboy |
Firm | Final Project Limit |
---|---|
Dinallo Construction Corp. | $314,253,266.00 |
Dobco, Inc. | $202,563,800.00 |
Epic Management, Inc. | $254,540,000.00 |
Intercontinental Construction Contracting Inc. | $202,563,800.00 |
Prismatic Development Corp. | $241,898,747.00 |
T.N. Ward Company | $688,500,000.00 |
Terminal Construction Corp. | $314,253,266.00 |
Tutor Perini Building Corp. | $807,661,008.00 |
Firm | Sub Consultants | Bid Amount | Price Points |
Price Rank |
Non Price Points |
Non Price Rank |
Weighted Price Points |
Weighted Non- Price Points |
Total Points | Final Rank |
---|---|---|---|---|---|---|---|---|---|---|
Terminal Construction Corp. | View | $247,950,000.00 | 100.000 | 1 | 74.167 | 1 | 60.000 | 29.667 | 89.667 | 1 |
Dinallo Construction Corp. | View | $247,950,000.00 | 100.000 | 1 | 74.167 | 1 | 60.000 | 29.667 | 89.667 | 1 |
Epic Management, Inc. | View | $252,252,000.00 | 98.295 | 2 | 71.417 | 2 | 58.977 | 28.567 | 87.544 | 2 |
Notes: In the table above, the pricing and scoring details are identical for Terminal Construction Corporation and Dinallo Construction Corporation based on their bidding status as a Joint Venture for this particular procurement action. Technical limitations prohibit the NJSDA from displaying these details on this website other than as represented in the table above. A copy of the original "NJSDA Price and Other Factors Bid Opening Worksheet" is available upon request.