Contract No. | Contract Name & Location | School District |
---|---|---|
ET-0061-B01 | Joseph C. Caruso E.S. | Keansburg |
Firm | Final Project Limit |
---|---|
Bedwell Company (The) | $62,509,530.00 |
Dobco, Inc. | $83,639,710.00 |
Epic Management, Inc. | $231,312,160.00 |
Ernest Bock & Sons, Inc. | $107,084,530.00 |
G&P Parlamas, Inc. | $25,437,347.00 |
Hall Building Corporation | $47,370,481.00 |
Hall Construction Co., Inc. | $131,295,840.00 |
Patock Construction Co. | $57,908,033.00 |
Prismatic Development Corp. | $103,600,000.00 |
Terminal Construction Corp. | $212,681,000.00 |
Firm | Sub Consultants | Bid Amount | Price Points |
Price Rank |
Non Price Points |
Non Price Rank |
Weighted Price Points |
Weighted Non- Price Points |
Total Points | Final Rank |
---|---|---|---|---|---|---|---|---|---|---|
Hall Construction Co., Inc. | View | $34,333,000.00 | 100.000 | 1 | 79.667 | 1 | 60.000 | 31.867 | 91.867 | 1 |
Ernest Bock & Sons, Inc. | View | $35,685,000.00 | 96.062 | 2 | 71.833 | 4 | 57.637 | 28.733 | 86.370 | 2 |
Epic Management, Inc. | View | $37,400,000.00 | 91.067 | 4 | 77.000 | 2 | 54.640 | 30.800 | 85.440 | 3 |
Hall Building Corporation | View | $36,491,000.00 | 93.715 | 3 | 63.833 | 5 | 56.229 | 25.533 | 81.762 | 4 |
Terminal Construction Corp. | View | $40,250,000.00 | 82.766 | 6 | 74.667 | 3 | 49.666 | 29.867 | 79.526 | 5 |
Dobco, Inc. | View | $38,852,000.00 | 86.838 | 5 | 35.833 | 6 | 52.103 | 14.333 | 66.436 | 6 |
Notes: