Contract No. | Contract Name & Location | School District |
---|---|---|
ES-0021-B01 | G.W. Carver Elementary School | East Orange |
Firm | Final Project Limit |
---|---|
Brockwell & Carrington Contractors, Inc. | $32,120,000.00 |
Dobco, Inc. | $144,019,723.00 |
Epic Management, Inc. | $245,490,000.00 |
Ernest Bock & Sons, Inc. | $169,622,902.00 |
Hall Building Corporation | $90,601,561.00 |
Hall Construction Co., Inc. | $153,723,281.00 |
Joseph A. Natoli Construction Corp. | $71,947,440.00 |
Terminal Construction Corp. | $199,471,000.00 |
Firm | Sub Consultants | Bid Amount | Price Points |
Price Rank |
Non Price Points |
Non Price Rank |
Weighted Price Points |
Weighted Non- Price Points |
Total Points | Final Rank |
---|---|---|---|---|---|---|---|---|---|---|
Dobco, Inc. | View | $26,900,000.00 | 100.000 | 1 | 65.833 | 2 | 60.000 | 26.333 | 86.333 | 1 |
Ernest Bock & Sons, Inc. | View | $28,538,000.00 | 93.911 | 2 | 64.167 | 3 | 56.346 | 25.667 | 82.013 | 2 |
Terminal Construction Corp. | View | $31,000,000.00 | 84.758 | 4 | 69.875 | 1 | 50.855 | 27.950 | 78.805 | 3 |
Brockwell & Carrington Contractors, Inc. | View | $29,560,000.00 | 90.112 | 3 | 50.833 | 4 | 54.067 | 20.333 | 74.400 | 4 |