Contract No. | Contract Name & Location | School District |
---|---|---|
ES-0018-P01 | Elementary School No.5 | East Orange |
Firm | Final Project Limit |
---|---|
APS Contracting, Inc. | $5,393,660.00 |
B&N&K Restoration Co., Inc. | $5,291,000.00 |
Cobra Construction Co., Inc. | $30,450,000.00 |
D&K Construction Co., Inc. | $33,300,000.00 |
Hilt Enterprises Inc | $2,000,000.00 |
Prime Environmental Services | $1,905,000.00 |
PSP Construction, Inc. | $1,547,500.00 |
Site Contractors Inc. | $4,176,000.00 |
Slavco Construction, Inc. | $3,050,967.00 |
Tricon Enterprises, Inc. | $2,000,000.00 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
Prime Environmental Services | $970,000.00 | View |
Tricon Enterprises, Inc. | $996,000.00 | View |
Slavco Construction, Inc. | $1,044,457.00 | View |
Hilt Enterprises Inc | $1,237,000.00 | View |
Cobra Construction Co., Inc. | $1,400,000.00 | View |
PSP Construction, Inc. | $1,431,000.00 | View |