Contract No. | Contract Name & Location | School District |
---|---|---|
ES-0007-C02 | Park Ave. ES Renovation & Addition | Orange |
Firm | Final Project Limit |
---|---|
Bergen Engineering Co. | $40,644,450.00 |
Cobra Construction Co., Inc. | $30,240,000.00 |
D&K Construction Co., Inc. | $50,650,000.00 |
Hall Building Corporation | $39,768,602.00 |
Hall Construction Co., Inc. | $57,504,960.00 |
Paul Otto Building Co., Inc. | $24,137,574.00 |
Watertrol, Inc. | $29,421,831.00 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
Hall Building Corporation | $23,545,000.00 | View |
D&K Construction Co., Inc. | $25,678,900.00 | View |
Bergen Engineering Co. | $26,379,000.00 | View |