Contract No. | Contract Name & Location | School District |
---|---|---|
EL-0007-C01 | New PreK-8 School #31 | Elizabeth |
Firm | Final Project Limit |
---|---|
AMCC Corporation | $60,547,200.00 |
Austin Helle Co., Inc. | $28,413,781.50 |
Bergen Engineering Co. | $40,107,200.00 |
Damon G. Douglas Company | $27,750,000.00 |
Eastern Contractors Inc. dba Motwane Construction | $74,137,238.66 |
Joseph A. Natoli Construction Corp. | $62,944,690.96 |
Petracca & Sons, Inc. | $66,772,292.62 |
Pike Construction Co | $76,700,000.00 |
Prismatic Development Corp. | $124,500,000.00 |
Terminal Construction Corp. | $132,589,500.00 |
Firm | Bid Amount | Sub Contractors |
---|---|---|
Prismatic Development Corp. | $33,689,000.00 | View |
Terminal Construction Corp. | $34,240,000.00 | View |
AMCC Corporation | $34,990,000.00 | View |
Bergen Engineering Co. | $36,244,000.00 | View |