Phillipsburg High School |
The new 330,000 square-foot school is designed to accommodate approximately 2,170 students in grades nine through twelve. The building includes 50 general classrooms, six special education classrooms, twelve small group instruction rooms, three health classrooms, twelve science related classrooms, three business labs, three computer labs, vocal and instrument music rooms, a media center, an auditorium, a cafeteria and a
gymnasium.
|
CURRENT STATUS - The project is substantially complete and the school is occupied. A ribbon cutting ceremony was held on September 21, 2016.
|
PROJECT INFORMATION
|
Key Parties:
Site Preparation Construction Contractor |
Epic Management, Inc. |
General Contractor |
Epic Management, Inc. |
Architect |
DIGroup Architecture, LLC |
Construction Manager |
Heery International, Inc. |
Schedule*:
Site Preparation Construction Activities |
Completed August 2012 |
Start of Building Construction |
November 2013 |
School Opening |
September 2016 |
Costs:
Total Estimated Project Costs |
$127.5 Million |
Total Construction Costs |
$80.5 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|