Paterson
New PS#16

EAST 21ST STREET & MADISON AVENUE

PATERSON, NJ



School #16
The new 109,500 square-foot, three-story facility is designed to educate approximately 700 students in grades Pre-kindergarten through eight. The new school replaces the existing building which was demolished. Demolition activities of the former school and surrounding properties were completed in April 2014. The school includes 22 general use classrooms, three kindergarten classrooms, four pre-kindergarten classrooms, specialized instruction classrooms and labs, a media center, a cafetorium, a gymnasium, as well as administrative and support facilities.

CURRENT STATUS - The project is substantially complete and the school is occupied. A ribbon cutting ceremony was held on September 20, 2016.

PROJECT INFORMATION

Key Parties:
Site Preparation Construction Contractor USA Environmental Management, Inc.
Design-Build Contractor Hall Construction Co, Inc.
Design-Build Architect DIGroup Architecture, LLC
Construction Manager GREYHAWK North America, LLC

Schedule*:
Site Preparation Construction Activities Completed April 2014
Design Design NTP issued January 17, 2014
Start of Building Construction September 2014
School Opening September 2016

Costs:
Total Estimated Project Costs $62.4 Million
Total Construction Costs $33.3 Million



*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.