Joseph A. Taub Middle School |
|
The new Joseph A. Taub MS project consisted of the construction of an approximately 160,000 SF building to educate a maximum of approximately 1,100 students in 6th through 8th grade on the site of the former Don Bosco School.
|
CURRENT STATUS - As of September 1, 2022: The project is substantially complete and occupied. A ceremonial ribbon cutting was held on December 14, 2021.
|
PROJECT INFORMATION
|
Key Parties:
|
Site Preparation/Demolition Construction Contractor |
Tricon |
|
Design-Build Contractor |
EPIC Management |
|
Design-Build Architect |
DMR Architects |
|
Construction Manager |
Cambridge/Anser |
Schedule*:
|
Site Preparation Construction Activities |
Completed July 2018 |
|
Design |
Design NTP 10/18/18 |
|
Anticipated Start of Building Construction |
July 2019 |
|
Anticipated School Opening |
September 2021 |
Costs:
|
Total Estimated Project Costs |
$113.9 Million |
|
*Please note that the anticipated milestone dates listed above are dependent on a number of variables and subject to change.
|
|